First scaled production - 60 tons of construction steel
Bara Eiendom, partner in Oppsirk ordered the first scaled production of hybrid construction steel to minimizing environmental impact. Delivered with steel from AF Offshore Decom, cleaned at Radøy Gr and produced at Alsaker steel. Design and project lead, Nordic Circles.
The building, called Link, will be completed in 2025. It has 60 tons of up cycled steel in the construction, mainly HSQ-beams. The steel origin is a FPSO called Curlew.
Pilot client: Bara Eiendom
Design and project lead: Nordic Circles
Steel supply: AF Offshore Decom
Research institute: Sintef
Production: Alsaker Steel and Radøygruppen
Curlew on its way to become construction steel at AF Offshore Decom in Vats Norway.
The ships hull being dismantled. Cut into steel plates, cleaned, tested and given a reuse report.